LINXS Construction Advisory


NIGHTLY STREET IMPACTS AT CENTURY BLVD. AND AVIATION BLVD.

Activity:

To facilitate construction activities for the Landside Access Modernization Program (LAMP), phased roadway impacts are scheduled at Century Blvd. and Aviation Blvd. nightly through Friday, August 4, from 11:00 p.m. to 6:00 a.m.

  • Phase I: Complete with minimal impact
  • Phase II: July 17–July 24, 2023 | Three lanes closed on westbound Century Blvd; left turn pocket to northbound Aviation Blvd. closed on eastbound Century Blvd.
  • Phase III: July 25–July 31, 2023 | Three lanes plus left turn pocket to northbound Aviation Blvd. closed on eastbound Century Blvd.
  • Phase IV: August 1–August 4, 2023 | Two lanes plus right turn to southbound Aviation Blvd. closed on eastbound Century Blvd.; one lane closed on southbound Aviation Blvd.

Access to local businesses will be maintained at all times. Watch for posted signage and always be alert when traveling through construction areas.


 

Dates/Times:

Nightly through Friday, August 4, 2023, from 11:00 p.m to 6:00 a.m.

 

*Dates and times subject to change.

 

Nightly Street Impacts

 

For additional information about the Landside Access Modernization Program, visit FlyLAX.com/ConnectingLAX.